WSJF: Prioritize Like a Product Ninja!

Alright, team, let’s talk prioritization. We’ve all been there. Staring at a backlog that’s longer than a CVS receipt, feeling the cold sweat of indecision. Do you tackle the big, hairy, scary feature first? Or maybe that quick win that’ll make your boss smile?

Enter Weighted Shortest Job First (WSJF). No, it’s not a new type of artisanal coffee. It’s a ridiculously effective way to figure out what to work on first to deliver the most value in the shortest amount of time. Think of it as the Marie Kondo of your backlog – we’re only keeping what sparks maximum business value.

WTF is WSJF (Really)?

WSJF is a prioritization method, primarily used in Agile frameworks (especially SAFe – the Scaled Agile Framework). At its core, it helps you determine the sequence of work. Consequently, it’s not just about picking what to do, but when to do it. It recognizes that time, like that last slice of pizza, is a precious, non-renewable resource.

The magic of WSJF lies in its focus on two key factors:

  1. Cost of Delay (CoD): What’s the impact of not doing this now? Will we lose revenue? Miss a market opportunity? Upset our users so much they start tweeting angry emojis?
  2. Job Size (or Duration): How long will this thing take to complete? A quick tweak or a multi-quarter saga?

By combining these, you can create the right order of importance.

The WSJF Formula Decoded

Here’s the magic equation:
WSJF = (User Value + Time Criticality + Risk Reduction) / Job Duration

sometimes people simplify (User Value + Time Criticality + Risk Reduction) to be Cost Of Delay

so the formula will look like WSJF = Cost of Delay/ Job Duration

  • User Value: How much customers want this feature
  • Time Criticality: Penalty for delaying delivery
  • Risk Reduction: Avoided disasters/enabled opportunities
  • Job Duration: Estimated effort

Job Duration/ Job Size – Sizin Up the Job (Size)

People tend to get tripped up on this. Job Size, also known as Duration.

We’re not trying to predict the exact number of hours or days something will take. Again, we’re using relative sizing or t-shirt sizing.

Consider:

  • Effort: How much work is involved?
  • Complexity: How many moving parts are there?
  • Uncertainty: How much do we not know about this?

How to Calculate WSJF: 3-Step Process

  1. Score Each Factor: Gather your squad and vote on values either using simple (1=quick, 10=marathon) or using Fibonacci sequencing (1,2,3,5,8,13) to avoid middle-ground bias.
  2. Crunch Numbers: Add User Value + Time Criticality + Risk Reduction, then divide by Job Duration.
  3. Sort & Conquer: Highest WSJF score wins the priority throne.

Pro Tip: Use a simple spreadsheet or Jira plugins like Ducalis to automate calculations

Real-World WSJF Wins

Example 1: E-Commerce Platform Overhaul

Imagine you’re on the product team for “Shoes ‘R’ Us,” an online shoe retailer. You have two features in your backlog:

  • Feature A: Implement a new “AI-powered shoe recommendation engine.” Sounds fancy, right?
  • Feature B: Fix a bug that causes the checkout process to crash 5% of the time. Not so fancy.

Let’s do some very rough WSJF estimation:

FeatureUser-Business Value (UV)Time Criticality (TC)Risk Reduction (RR)Job SizeWSJF
A (Recommendation Engine)53281.25
B (Checkout Bug)88537

Even though the AI engine sounds cooler, fixing the checkout bug has a much higher WSJF score. Why? Because that 5% crash rate is bleeding money right now. The Cost of Delay is sky-high.

Example 2: Healthcare App Compliance

Dilemma: Update legacy system vs. add telehealth features

WSJF Analysis:

TaskUVTCRRJSWSJF
Compliance5131356.2
Telehealth135883.25

Result: Compliance work prioritized, avoiding $2M in potential HIPAA fines

Pro Tips for WSJF Success

  • Beware of Sandbagging: Teams sometimes inflate Job Duration scores – combat this with historical velocity data.
  • Reassess Weekly: Priorities change like TikTok trends – update scores during sprint reviews.
  • Combine Frameworks: Use WSJF with RICE scoring for complex decisions involving multiple stakeholders.

FAQ: WSJF Edition

Q: Can WSJF work for bug fixes?
A: Only if they’re showstoppers – minor bugs often score low on Time Criticality

Q: How is this different from RICE?
A: WSJF adds time pressure and risk factors – RICE focuses on reach/confidence

Q: Best WSJF software?
A: Jira + Advanced Roadmaps or ClickUp’s formula fields work wonders

WSJF ≠ Crystal Ball (But Close)

While no framework guarantees success, WSJF turns prioritization from political debates into data-driven decisions.

  • Making informed decisions: It forces you to think critically about value and urgency.

  • Facilitating conversations: It provides a common language for stakeholders to discuss priorities.

  • Adapting to change: As new information emerges, you can re-calculate WSJF and adjust your plans.
  • Maximizing Flow. Small quick work promotes flow.
  • One SAFe team at a retail giant used it to reduce decision-making time by 40% while increasing ROI per sprint.Ready to WSJF your backlog into shape?

    Your product roadmap will thank you later

    0 Comments

    Leave a Reply

    This site uses Akismet to reduce spam. Learn how your comment data is processed.

    ©2025 Luke Angel

    Log in with your credentials

    Forgot your details?

    %d bloggers like this: